E- TIMETABLE
- WP1+WP2 until July 96
- WP3.1 between May and end of October 96
- WP3.2 between end of October and mid February 97
- WP4 between February and March 97
- WP5 April 96; October 96; February 97
- WP6 During all X-MAS life
Milestones
- M: 11/4/96; 28/10/96; 13/2/97
- W: 29/10/96; 14/2/97
- R: July 96; March 97
Notation
- M - X-MAS Meeting
- W - X-MAS Worksop including non-Academics
- R - Report
- WP1 - Description of Petrobras application Requirements / CEFET
- WP2 - Description of Riocel application Requirements / UFRGS
- WP3 - 3.1 - First Specifications of MAS for selected Applications/QM+FEUP+UTC
3.2 - Advanced Specifications on MAS for selected App./QM+FEUP+UTC
- WP4 - Writing Reports / FEUP+QMWC+UTC
- WP5 - Meetings + Workshops preparation /CEFET + UFRGS + FEUP
- WP6 - Project coordination / FEUP